Industrial licences: from establishment to production
A factory is licensed in stages on the Ministry of Industry and Mineral Resources' Senaei platform. The first industrial licence lets you set up the project but not produce, and is valid for one year; the project then moves to the construction stage and, once the factory is producing, to production status, which opens all the ministry's industrial services.
General guidance, not legal or tax advice. Rules and fees change: confirm what applies to you before acting.
The three stages
- Establishment: an industrial licence that lets the investor complete the requirements for setting up the project. It is valid for one year only and does not allow production. It needs a valid commercial registration that includes the industrial activity.
- Construction: once the establishment requirements are met, the licence is upgraded to the construction stage. It is valid for one year, still does not allow production, and makes the project eligible for customs exemption on machinery and spare parts and for partial labour support.
- Production: once production has started and requirements are met, the licence is upgraded to production, giving access to all industrial services, such as raw-material customs exemptions, labour support and certificates of origin.
Site
You need an industrial site that suits the activity. Through the ministry's site allocation service you can apply for land with MODON (the Saudi Authority for Industrial Cities and Technology Zones) or the Royal Commission for Jubail and Yanbu, or declare a site with another body. The site affects environmental and Civil Defense requirements, so decide it early.
Keeping the licence current
- Renew the licence before it expires; renewal can extend its validity for up to five years once all requirements are met.
- Amend it when products, machinery, raw materials or the location change.
- Submit the periodic industrial survey, which keeps your records current with the National Center for Industrial and Mining Information.
- Cancel it permanently through the ministry if the factory closes.
Foreign investors
A foreign-owned manufacturer registers its investment with the Ministry of Investment first, forms the company and obtains the commercial registration, then applies for the industrial licence. Industrial development financing from the Saudi Industrial Development Fund is applied for separately.
Questions people ask
No. The establishment and construction stage licences do not allow production. You need the production status.
Customs exemption for machinery and spare parts becomes available at the construction stage.
Often yes, depending on the activity's environmental classification and the site. Check during the establishment stage.
How we can help
Sources (5)
- Ministry of Industry and Mineral Resources: issuance of an industrial licence
- Ministry of Industry and Mineral Resources: upgrading the licence to the construction stage
- Ministry of Industry and Mineral Resources: upgrading the licence to production
- Ministry of Industry and Mineral Resources: renewing an industrial licence
- Ministry of Industry and Mineral Resources: industrial site allocation
General guidance, not legal advice. Rules change and vary by case; we confirm what applies to you before anything is filed.
Related guides
Setting up a manufacturing company in Saudi Arabia
Read the guide Market entryIndustrial cities and MODON
Read the guide Market entrySpecial economic zones in Saudi Arabia
Read the guide Government platformsAramco's iktva programme
Read the guide Documents and official stampsCertificates of origin for Saudi exports
Read the guideThe Saudi company setup checklist
Every step from choosing a structure to your first year of compliance, in order, as a printable PDF.
Bring us the question your file is stuck on.
Thirty minutes, free, with a reply within one working day.